This section includes the following works:

 

1 –  Installing pipelines to repair oil lines.

2 –  Connecting the water pumping lines to the main lines.

3 –    Removing sand from petroleum lines.

4 –    Mechanical works in gas-oil separation plants.

5 –  Paving and grading roads for oil or water pipelines.

6 –  Leveling and network protection works for oil wells.

7 –  Maintenance of water lines.

8 –  Upgrading the oil eyes, constructing new oil lines and connecting them to the oil factories.

9 –  Construction of water injection lines directed towards the oil plant.

10 –    Connecting wells to oil plants.

11 –  Development of reverse osmosis plants at gas plants.

12 –  Connecting the eyes of water injection to the oil factories.

13 –  Updating the drainage systems of the oil works areas.

 

 

The company’s most important achievements in the field of petroleum pipelines are as follows:

 

Project No. Project owner name Project name Project location date of contract signing Business description
180

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Connecting 29 water injection wells to Oil Plant No. 3 in Haradh pit 2005-04-03

– Construction and extension of pipelines for 29 water wells and linking them to Water Injection Plant No. 3 in Haradh, with a total length of 31 km and a diameter of 10 inches.

– Provide all necessary labor, equipment and materials to finish the work according to the requirements of Saudi Aramco, and put wells in use for water injection.

182

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Uthmaniye Wells Connecting No. 1588, 1585, 1587, 1589, 1586, 1596

In the oil refinery No. 10 in Othmaniye and linking well 1573 to the oil plant No. 11 in Othmaniye

Ottoman 2005-09-05

– Construction and extension of pipelines for 7 crude oil production wells, and linking them to the oil-gas separation plant No. 10 and 11 in the Othmania area.

– Work the main lines to transport the oil from these wells to the sorting plant with a total length of 22 km and different diameters ranging from 8, 10, 16 inches.

– Providing all the necessary labor, equipment and materials to finish the work according to the requirements of Saudi Aramco, and putting the wells into use for oil production

193

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Connecting the notables of al-Zayt to the Al-Hotah area, lane 57 and 25, Hawtah 83

Neem 36 and 37 at Al-Houta Oil Factory

Naeem, Hawtah and Ghaneh 2006-07-05

– Construction and extension of pipelines for 3 oil-producing wells in Al-Houta, and linking them to the oil-gas separation plant in Al-Houta.

– Construction and laying of pipelines for two water injection wells with different diameters of 4, 6, and 8 inches.

– Providing all the necessary labor, equipment and materials to complete the work according to Aramco’s requirements and to ensure that wells are put into use for water injection as well as crude oil production.

197

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Connecting Hawiyah Wells No. 528, 532, 534 to Hawiyah Oil Factory No. 4

With 97 fencing around Haradh Oil Factory No. 2

Hawiyah and Haradh 2006-12-23

– Construction and laying of pipelines for 3 wells for the production of crude oil Nos. 528, 532, 534 and linking them to the oil-gas separation plant No. 4 in Al-Hawiya area with diameters of 8 inches and a length of about 5 km.

– Making a secure net around 97 oil wells around the oil-gas separation plant No. 2 in Haradh.

– Providing all the necessary labor, equipment and materials to finish the work according to the requirements of Saudi Aramco.