Abdul Rahman Al Bader Sons Company
Trading and Contracting

Construction Department

 

This section includes the following works:

 

[1] Building works ..includes concrete and steel works.

 

[2] Road works ..which includes earthworks for the construction of roads.

 

[3] Water and sewage works..which include water and sewage stations, water networks, pumping stations and torrential networks.

 

[4] Electrical works .. It includes power generation plants, power transmission and distribution and cathodic protection.

 

[5] Mechanical works .. It includes the central cooling and air conditioning system and water pumping stations.

 

[6] Industrial Business Division .. It includes water desalination plants and oil and gas networks.

 

 

 

The company’s most important achievements in the field of petroleum pipelines are as follows:

 

Project No. Project owner name Project name Project location date of contract signing Business description
298

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Water tank treatment in pits ridges 1/12/2019

– This project is one of the interesting projects that have been assigned to the company by Saudi Aramco, and the company has carried out the project beginning with drawings and Engineering designs and all construction and painted materials, whether from the local or foreign market

230

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Maintenance of water lines 1 and 2 from the village to the Ottoman – Phase One Al Qaria 2008-08-25 Maintenance of water lines No. 1 and 2 from Al-Qurayya to the Ottoman between
Kilometers 18 and 26, including excavation and cover removal
and the lining on the pipeline and welding works
packing, testing, backfilling and leveling
242

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Pre-operating support for 32 inches of MMF 2 in Jubail. Jubail 1433-08-11 Pre-boot support for 32″ in 2-in methane feed Jubail.
244

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Create a new molten sulfur mine in QSWP Al Qaria 1433-09-14 – Create a new molten sulfur mine in QSWP
245

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Extension of type 4 fencing at Dammam Field B drilling site Dammam 1433-11-17 – Extension of type 4 fencing at the Dammam Field B excavation site
247

“University of Dammam”

Renovation, development and modernization of the swimming pool in residential complex No. 1 at King Fahd Hospital University of Khobar khobar 1433-12-19 -Renovation, development and modernization of the swimming pool in the complex
Residential No. 1 (King Fahd University Hospital, Al-Khobar
248

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Fence for twenty forty houses, the Ottoman Empire and the Hawiye Hawiyah 1433-12-19 -Fence of twenty wells at Ain Dar and the Ottoman
and hawiyah
252

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Civil works for the Abqaiq power transmission system development project Abqaiq 1434-08-17 – Civil works of the Abqaiq power transmission system development project.
255

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Mechanical injection skates in Khobar Khurais 1435-01-14 – Installing a base for chemical tanks in Khurais.
256

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Construction of foundations and access road to electrical equipment yard at Abqaiq plant Abqaiq 1435-11-204 -construction of foundations and access to equipment yard
Electricity at Abqaiq Factory.
257

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

Removing the sand from inside and outside the grid for 77 springs in the Khurais area Khurais 1435-02-27 – Removing sand from inside and outside the grid for 77 eyes in Khurais  
258

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

 

Removing the sand from inside and outside the grid for (74) eyes in the Khurais area Khurais 1435-02-21 – Remove sand from inside and outside the grid for (74) eyes in Khurais.
260

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

 

Construction of a generator room and transformer for the endoscopy and intensive care building and a waste room at King Fahd University Hospital in Al-Khobar khobar 1435-05-01 – Project of constructing a generator room and transformer for the endoscopy and intensive care building and a waste room at King Fahd University Hospital in Al-Khobar. 
266

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

 

Upgrading the drainage system at the Qurayya Seawater Injection Plant Al-Qurayya 1435-07-27 – Updating the drainage system at the Qurayya seawater injection plant.
273

Arabian Oil Company

Saudi Arabia

“Saudi Aramco”

 

Abqaiq factory drainage pond restoration (2) Baqiq 1437-03-16 – Restoration and repair of the drainage pool at Abqaiq Factory (2).